Even with the unexpected heavy rains that devastated much of
the surrounding area in the upper Midwest, the groundwork for this addition was
still largely completed by mid-June.
The first support column was erected on
June 25, 2008.
Upper level steel grid work began on
June
30, 2008 with the metal cover in place by July 15, 2008.
Mid-July 2008, concrete block going up on the North wall. Siding
added on West wall
July 31, 2008.
Sealing the Roof on August 6 and a quick look inside on August 7, 2008.
North
Wall Completed August 12, 2008.
East
(Last) Outer Wall in progress.
August 18, 2008 - Insulation