Torrance Casting News

New Remittance Address 

Starting July 1, 2008, we will request payments be sent to our new Remittance Address:

Torrance Casting, Inc.
Lockbox 791
La Crosse, WI  54602-0791

 

Building Expansion - Summer of 2008 

In May of 2008, we started a building expansion project on the North side of our facility. This 14,000 square foot addition is part of a $2.5 million expansion project to increase the production capacity of our sand system and further improve our sand quality. It will also greatly improve the product flow through our cleaning department. This expansion project is slated to be completed in mid-October, 2008.

 

 

This is the initial phase of an overall $8 million capital expenditure program. Within the next 2-3 years, we will further streamline the product flow within our cleaning department, add two additional melting furnaces and add a 32x32 DISA Matchplate Automatic Molding System.  The net effect of these changes will be to double our overall plant capacity to produce quality castings for our customers. We are excited at the possibilities this addition will bring to our customers.

 

 

As you can see, even with the unexpected heavy rains that devastated much of the surrounding area in the upper Midwest, the groundwork for this addition was still largely completed by mid-June with the first support column being erected on June 25, 2008.

 

 

 

Upper level steel work almost complete.
June 30, 2008  

 

 

 

Covering the addition.
July 9, 2008.

Cover in place
July 15, 2008.

 

 

Continuing to take shape.
July 18, 2008.    

 

 

 


Concrete block on North wall.
July 24, 2008.

 

 

 

 

Siding added on West wall.
July 31, 2008.

 

 

 


Sealing the Roof.
August 6, 2008.

 

 

 

A look inside.
August 7, 2008. 

 

 

 

North Wall in process.
August 8, 2008.

 

 

 

North Wall Completed.
August 12, 2008.

 

 

 

East (Last) Outer Wall in progress.
August 13, 2008.

 

 

 

Placing the panels on the last wall.
August 14, 2008.

 

 

 

 Almost Finished - Better turn on the lights.
August 15, 2008. 

    

 

 

Insulation up - Outside walls complete!
August 18, 2008.

 

 

 

Check back for further updates..!